OUR ACHIEVEMENT

Tallest Tower - Cold Insulation Refurbishment in Pasir Gudang, Johor

  • L.K. is the first and sole capable company within its region to refurbish with tower in vertical position.
  • Good Safety control with no accident & labor wastage during tight schedule.
  • Good Quality control on the towers insulated as proven to-date after three years of refurbishment.

Power Plant Insulation at Lumut, Perak

  • Good Safety control with no accident & labor wastage during tight schedule.
  • Good Quality control and Schedule management which resulted the said job completed ahead of schedule. Contributed to the “Completed in Record Time Achievement” as celebrated by Alstom.

Contract Insulation with Petrochemical Plants

  • Good Safety control with no accident & labor wastage during three years contract.
  • Good Quality control on insulation application.
  • Work Scope
    • Daily Insulation Maintenance
    • Completion of four turnaround works during contract services time.

Refractory Project at Port Dickson

Client: Shell Refinery, Port Dickson
Main Contractor: JGC, Japan
Sub contractor: Plibrico Japan Ltd/ LK Insulation
Project: LRCC Plant Refractory Work

  • Successfully completion of job within thirteen months under the supervision of respected Mr. Nakagawa (Plibrico, Japan).

Fabrication Work at High Temperature Expansion Joint

Client: MLNG 3, Bintulu
Main Contractor: JGC, Japan
Sub contractor: AAM Japan Ltd. / LK Insulation
Project: High Temp. (1300°C) Expansion Joint 2nos

  • Successfully carried out the highest service temperature expansion joint within agreed timeframe.

Gas Turbine Expansion Joint

Client:
TNB, Power Station – Pasir Gudang, Serdang, Connaught Bridge and Paka.
IPP Power – Pahlawan Power at Malacca.
Material supply: KE-Burgamann & Deconte Brand
Number installed: More than 30 sets

  • With the use of our special tools, the installation of expansion joints was reduced to five to ten days depending on size.

The Most Challenging AchievementCompletion of Insulation, Painting and Scaffolding Work for 3 towers within 30 days

  • Bad Condition of Towers before removal of Insulation on Tower 410, Tower 420 & Tower 470 which were was causes by swatting at Titan Petrochemical (M) Sdn. Bhd, Johor.
  • The Height and Diameter are as follows:
    • 1.  Tower 410 : 2.1 dia x 48H
    • 2.  Tower 420 : 1.2 dia x 55H
    • 3.  Tower 470 : 2.6 dia x 75H
  • Erection of Scaffolding on Tower 410, Tower 420 & Tower 470 at Titan Petrochemical (M) Sdn Bhd, Johor
  • Scaffolding that was build around the tower are as follows:
    • 1. Tower 410 : 4.8m x 4.8m x 47mH
    • 2. Tower 420 : 3.6m x 3.6m x 57mH
    • 3. Tower 470 : 5.4m x 5.4m x 79mH
  • Erection of Scaffolding on Tank T-5101 at Idemitsu SM (Malaysia) Sdn Bhd and completion within one week time frame.
  • The Height and Diameter of Tank T-5101:
    OD: 34.0m x 32.0mH

OUR EXPERIENCESProjects done by LKM on year 2018

Service Range Client Type of Work Work Description Location of Job
Oil, Gas & Petrochemical Industry DIALOG PLANT SERVICES INSULATION PROJECT: Insulation works at PDT2 CO Line in Pengerang PENGERANG (JOHOR)
Oil, Gas & Petrochemical Industry HQC ENGINEERING SCAFFOLDING Scaffolding works for Package 28A RAPID (JOHOR)
Oil, Gas & Petrochemical Industry HQC ENGINEERING SCAFFOLDING Scaffolding works for Package 14 (Pipe rack) RAPID (JOHOR)
Oil, Gas & Petrochemical Industry MSL HARVEST & ENGINEERING SCAFFOLDING Contracting Scaffolding works for Rapid 2018 RAPID (JOHOR)
Manufacturing Industry SEAGATE PAINTING, SCAFFOLDING Painting & Scaffolding work at Basement Floor Plan of Stair 9 Area SENAI (JOHOR)
Manufacturing Industry SEAGATE PAINTING, SCAFFOLDING Painting & Scaffolding work for Cooling Tower 8A & 8B SENAI (JOHOR)
Oil, Gas & Petrochemical Industry SYNTHOMER INSULATION PROJECT: Insulation SDM June 2018 PASIR GUDANG (JOHOR)